Project Milestone Status

Project Milestones Status

Project Milestone Description (Days from Appointed Date) Planned Actual Delay (No. of months) Current Status
Physical Progress (%) Scheduled Date Physical Progress (%) Achieved Date
Project Milestone-I 150 20 12.04.2023 23.65 % 25.03.2024 NA w.r.t BPC-1  
Project Milestone-II 330 35 09.10.2023 36.41% 31.01.2025 NA w.r.t BPC-1  
Project Milestone-III 510 75 06.04.2024 54.30% 08.05.2025 NA w.r.t BPC-1 54.30%
Schedule Completion 730 100 12.11.2024