| Component | %Weightage as per Schedule-G | Progress achieved (during current month) | Physical Progress achieved (Cumulative, up to current month) |
|---|---|---|---|
| Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) | 60.50% | 1.18% | 39.601% |
| Major Bridge Works & ROB/ RUB | 15.63% | 0.65% | 13.517% |
| Structures (elevated sections, reinforced earth) | 2.84% | 0.02% | 1.933% |
| Electrical and Public Health Utilities | 0.56% | 0.00% | 0.315% |
| Other Works | 20.46% | 0.36% | 6.694% |
| Total | 100% | 2.217% | 62.06% |