| Project Milestone | Description (Days from Appointed Date) | Planned | Actual | Delay (No. of months) | Current Status | ||
|---|---|---|---|---|---|---|---|
| Physical Progress (%) | Scheduled Date | Physical Progress (%) | Achieved Date | ||||
| Project Milestone-I | 150 | 20 | 12.04.2023 | 23.65 % | 25.03.2024 | 11 Months | |
| Project Milestone-II | 330 | 35 | 09.10.2023 | 36.41% | 31.01.2025 | 15 Months | |
| Project Milestone-III | 510 | 75 | 06.04.2024 | PC issued for 26.005 km under BPC-1 w.e.f. 01.03.2026 and 12.995 km under BPC-2 to be completed by 14.12.2027.) |
72.82% |
||
| Schedule Completion | 730 | 100 | 12.11.2024 | ||||
| *PC issued for 26.005 km under BPC-1 w.e.f. 01.03.2026 within the approved EOT till 02.03.2026. | |||||||