Physical Progress

Physical Progress

Component %Weightage as per Schedule-G Progress achieved (during current month) Physical Progress achieved (Cumulative, up to current month)
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) 60.50% 0.31% 44.109%
Major Bridge Works & ROB/ RUB 15.63% 0.06% 14.332%
Structures (elevated sections, reinforced earth) 2.84% 0.04% 2.631%
Electrical and Public Health Utilities 0.56% 0.00% 0.422%
Other Works 20.46% 0.00% 11.329%
Total 100% 0.415% 72.82%