Component | %Weightage as per Schedule-G | Progress achieved (during current month) | Physical Progress achieved (Cumulative, up to current month) |
---|---|---|---|
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) | 60.50% | 0.91% | 35.933% |
Major Bridge Works & ROB/ RUB | 15.63% | 0.27% | 11.973% |
Structures (elevated sections, reinforced earth) | 2.84% | 0.16% | 1.789% |
Electrical and Public Health Utilities | 0.56% | 0.00% | 0.315% |
Other Works | 20.46% | 0.54% | 5.607% |
Total | 100% | 1.876% | 55.62% |