Project Milestone | Description (Days from Appointed Date) | Planned | Actual | Delay (No. of months) | Current Status | ||
---|---|---|---|---|---|---|---|
Physical Progress (%) | Scheduled Date | Physical Progress (%) | Achieved Date | ||||
Project Milestone-I | 150 | 20 | 12.04.2023 | 23.65 % | 25.03.2024 | NA w.r.t BPC-1 | |
Project Milestone-II | 330 | 35 | 09.10.2023 | 36.41% | 31.01.2025 | NA w.r.t BPC-1 | |
Project Milestone-III | 510 | 75 | 06.04.2024 | 54.30% | 08.05.2025 | NA w.r.t BPC-1 | 54.30% |
Schedule Completion | 730 | 100 | 12.11.2024 |