| Particulars | Details/Status |
|---|---|
| Project Name | Development of 6-Lane Amritsar-Bathinda Greenfield section of NH-754A from village Tiba on NE-5A to junction with Moga Jalandhar road (NH-703) near Dharmkot (from km 0+000 to Km 39+000) as a part of Amritsar-Jamnagar Economic Corridor in the state of Punjab on Hybrid Annuity Mode under BharatmalaPariyojana Phase-I (Package-1) |
| NH No. (New/old) | NH-754A |
| Scheme/Phase | Bharatmala Pariyojana |
| Mode of Execution | Hybrid Annuity Mode (HAM) |
| Concessionaire Name | M/s G R Amritsar Bathinda Highway Private Limited |
| Date of Letter of Award (LOA) | 23.09.2021 |
| Appointed Date | 14.11.2022 |
| Construction Period (in Days) | 730 Days from the Appointed Date |
| Schedule Completion Date | 12.11.2024 |
| Operation & Maintenance Period | 15 years from COD |
| Independent Engineer | M/s Chaitanya Projects Consultancy Pvt. Ltd. In JV with M/s K&J Projects Pvt. Ltd. & in Association with M/s INFRAILLUMINATIONS LLP, Ghaziabad |
| Authority Name | National Highways Authority of India, PIU-Jalandhar |
| Independent Engineer Mobilization Date | 01.12.2022 |
| No. of Lanes/ Configuration | 4/6 Lane |
| Bid Project Cost | 927.00 Cr. |
| Total Length of the Project | 39.000 km |
| No. of Interchanges | 03 nos. |
| No. of ROB | 02 nos. |
| No. of Flyovers | 01 no. |
| No. of Underpasses | VUP-01 no., LVUP-03 nos., SVUP-40 nos.+ 5 nos. additional |
| No. of Major Bridges | Over rivers, streams, nallas: 01 no. Over irrigation canals: 01 no. |
| No. of Minor Bridges | Over rivers, streams, nallas: 04 nos. Over irrigation canals: 01 no. |
| No. of Culverts | Box Culverts for Cross-drainage: 32 nos. Box Culverts for Connecting Roads/Road cum drain: 17 nos. Box Culverts for Interchanges: 23 nos. Hume Pipe Culverts for field canal/ Utility crossing: 39 nos. |
| Toll Plaza | 02 nos. |